Dupleix and Nationale stations are closed in the evenings until October. Learn all about it.

Traffic resumed between Montparnasse - Bienvenüe and Trocadéro stations on 28 August, after a summer of works related to the upgrade of metro line 6 and the renovation of its viaduct. Many thanks for your patience! And well done to the teams who mobilized all summer for this major project. For a look behind the scenes of the work site, click here

Closure of Dupleix station at 10:00 p.m. each evening until 1 October inclusive

As part of the facilities maintenance policy for metro line 6, RATP is continuing its work during the summer of 2021 with the renovation of the fixed stairway at Dupleix station. After a first construction phase carried out during the summer, finishing works will be necessary in the evenings from 28 August to 1 October inclusive, with the station closing from 10:00 p.m. Trains will not stop at the station. 

Closure of Nationale station at 10:00 p.m. each evening until 15 October 2021

As part of the facilities maintenance policy for metro line 6, we are continuing our works during the summer of 2021 with the renovation of the fixed stairway at Nationale station. The station will close at 10:00 p.m. from 28 August to 15 October 2021 inclusive. Trains will not stop at the station.

Last year of the metro line 6 viaduct renovation project

A fixture of the Paris skyline, the renovation of the metro line 6 viaduct between Passy and Pasteur stations came to an end this summer. The structure, built over a century ago, has stood the test of time remarkably well and weathered the colossal growth in traffic. A work program began 1997 to maintain and repair it. The last step of the project concerned waterproofing and painting work between Montparnasse - Bienvenüe and Trocadéro stations. 
In total, the project involved:

  • 3,370 meters of track renewed, of which 1,900 meters in 2021,
  • 5,670 metric tons of ballast replaced, of which 3,200 tons in 2021,
  • 1,215 linear meters of painting, of which 580 linear meters in 2021

Find out more

All RATP teams are ready to guide and support you during the closure of linemetro symbole metro ligne 6 Many educational and informative tools will soon become available to allow you to best prepare for the service interruption periods on the line (to see the line map, click here).

Until then, you can visit our social networks pages, notably our métro line 6 Twitter account.