Network modernisation

Metro line 11: works and closures

As part of its future extension, metro line 11 is set to close on several occasions over the coming months.

To prepare for the spring 2024 launch, testing continues on Line 11. Therefore, the line will be closed:

  • On Sunday, April 28, 2024, the line will be completely closed. A substitute shuttle service will be provided.
  • From Friday, April 12 to Saturday, April 27, 2024, the line will be closed between Belleville and Mairie des Lilas stations.

calendrier des fermetures de la ligne 11 au premier trimestre 2024

  • From April 28th to May 29th, 2024, due to platform adaptation works for the introduction of the new rolling stock MP14, trains will not stop at Porte des Lilas station towards Mairie des Lilas. The station remains served towards Châtelet.
fermeture quai porte des lilas

The elevator at Porte des Lilas station is currently under construction. It will be back in service by the end of September 2024, enabling the accessibility upgrade of Porte des Lilas station.

The closures will allow for testing of the new MP14 trains on the existing line in preparation for its extension. We encourage you to use alternative metro, bus, RER, and tramway lines for your travel needs. Our station agents are available to assist you with information on the timing of the last train at each station and to provide further details as needed.


schéma de perturbation des travaux de la ligne 11 au premier trimestre 2024

To adapt your journey

This page is regularly updated to reflect works and closures on the line.

Modernisation Travaux Ligne 11